City of Daytona Beach Sealed Solicitation

Title: A1A & ISB INTERSECTION LANDSCAPING

Deadline: 5/30/2019 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 19453

Description:

The work generally consists of installing landscape and irrigation at the western intersection of
International Speedway Boulevard and Atlantic Avenue (A1A), at both the north and south corners, to assist the City with meeting its goal to provide an aesthetically acceptable restoration of the intersection.
Project Magnitude is $85,000 - $105,000.


Pre-Bid Meeting Date: 5/7/2019 10:00 AM

Pre-Bid Meeting Details: A NON-MANDATORY PRE-PROPOSAL CONFERENCE will be held at the Daytona Beach Public Works, 950 Bellevue Ave, #500, Daytona Beach, Florida 32114, on May 7, 2019 at 10:00 AM. Interested contractors are urged to attend.


Documents:

Documents as of 6/12/2019
ITB-INVITATION - 19453.pdf
ITB 19453-ISB & A1A LANDSCAPING.pdf
ITB-PLANS_A1A-ISB LA-IR 3-13-19 NNotesVer.pdf
Prebid Sign-in sheet 19453.pdf
BID TAB-19453.pdf
NOTICE OF INTENT TO AWARD 19453.pdf
Addition 1

Posted: 5/7/2019

Type of Addition: Addendum 1

Overview: revised bid schedule.

Documents:

Addition 2

Posted: 5/15/2019

Type of Addition: Addendum 2

Overview: question about cost of bonding.

Documents:

Addition 3

Posted: 5/21/2019

Type of Addition: Addendum 4

Overview: Questions & Answers

Documents:

Addition 4

Posted: 5/21/2019

Type of Addition: Addendum 3

Overview: Questions & Answers

Documents:

Addition 5

Posted: 5/31/2019

Type of Addition: In Review

Addition 6

Posted: 7/23/2019

Type of Addition: Award Information

Documents:

Question 1

Posted: 5/20/2019

Question: 1. Are we to demo the existing concrete in conflict with the landscaping and irrigation? If so, what is the square feet of the demo for the concrete and asphalt required? 2. Regarding the meter on the south side: On the flow side of that meter, does that line extend under the concrete to the area needed, or will we have to demo and replace the sidewalk? 3. Are we to price the decorative fence and if so is there a line item?

Response: 1. Concrete demo will be done by others prior to Notice to Proceed. 2. See #1 3. Fence work to be done by others. Not included in the Scope of Work

Posted: 5/7/2019

Type of Addition: Addendum 1

Overview: revised bid schedule.

Documents:

Posted: 5/15/2019

Type of Addition: Addendum 2

Overview: question about cost of bonding.

Documents:

Posted: 5/21/2019

Type of Addition: Addendum 4

Overview: Questions & Answers

Documents:

Posted: 5/21/2019

Type of Addition: Addendum 3

Overview: Questions & Answers

Documents:

Posted: 5/31/2019

Type of Addition: In Review

Posted: 7/23/2019

Type of Addition: Award Information

Documents:

Posted: 5/20/2019

Question: 1. Are we to demo the existing concrete in conflict with the landscaping and irrigation? If so, what is the square feet of the demo for the concrete and asphalt required? 2. Regarding the meter on the south side: On the flow side of that meter, does that line extend under the concrete to the area needed, or will we have to demo and replace the sidewalk? 3. Are we to price the decorative fence and if so is there a line item?

Response: 1. Concrete demo will be done by others prior to Notice to Proceed. 2. See #1 3. Fence work to be done by others. Not included in the Scope of Work