Dorchester County Sealed Solicitation

Title: On-Call Contract for Water & Sewer Engineering Services

Deadline: 9/17/2020 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: RFQ 2021-05

Description:

Dorchester County is requesting proposals from qualified, multi-disciplined engineering firms to perform engineering and consulting services for water and wastewater related projects on a task-oriented basis.


Documents:

Documents as of 8/17/2020
Login to view documents
Addition 1

Posted: 9/3/2020

Type of Addition: Addendum

Overview: This addendum extends the due date and time to September 14, 2020 at 2:00 PM Eastern Time.

Documents:

Addition 2

Posted: 9/4/2020

Type of Addition: Addendum

Overview: This addendum answers questions and adds two additional attachments.

Documents:

Addition 3

Posted: 9/10/2020

Type of Addition: Addendum

Overview: This addendum changes the due date and time and clarifies the number of submittals.

Documents:

Addition 4

Posted: 9/17/2020

Type of Addition: In Review

Addition 5

Posted: 12/4/2020

Type of Addition: Award Information

Overview: Contracts have been awarded to the top five scoring firms in each category. Please see the memo excerpt attached.

Documents:

Question 1

Posted: 8/18/2020

Question: 1. Please confirm that one proposal can be submitted for all three categories of scope of work. 2. As the proposals can be submitted electronically or mailed/hand delivered, will electronic submissions be printed for review or viewed online only?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Question 2

Posted: 8/18/2020

Question: 3. Please confirm a consolidated financial statement is acceptable in lieu of an audited statement. 4. The last page of the Response Format section notes providing resumes for key staff members in one bullet and the following bullet notes providing resumes in the appendix, should all resumes be included in the appendix as opposed to the body of the document?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Question 3

Posted: 8/21/2020

Question: What is the page limit for an electronic submittal? 50 or 100 pages?

Response: 50 pages front and back for submission of a physical copy; 100 pages electronically.

Question 4

Posted: 8/24/2020

Question: Please provide a copy of the current Dorchester County CIP for reference.

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Question 5

Posted: 8/25/2020

Question: Would you like one submittal for each category we are submitting on, or just one submittal total with combined qualifications?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Question 6

Posted: 8/28/2020

Question: 6. Does DCWS have an existing water system model and if so, what hydraulic modeling software platform was used?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Question 7

Posted: 8/28/2020

Question: In Section C, the RFQ asks for the following item: Current and projected workloads of the Firm. Please provide a summary document identifying the project data demonstrating the Firm’s ability to meet project time and budget requirements for up to the most recent 15 similar projects undertaken by the Firm Does the County wish us to provide 15 of our current and projected workload/projects per the first sentence? Or does the County wish us to provide 15 recent previous projects to capture our ability to meet time and budget requirements per the second sentence?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 9/3/2020

Type of Addition: Addendum

Overview: This addendum extends the due date and time to September 14, 2020 at 2:00 PM Eastern Time.

Documents:

Posted: 9/4/2020

Type of Addition: Addendum

Overview: This addendum answers questions and adds two additional attachments.

Documents:

Posted: 9/10/2020

Type of Addition: Addendum

Overview: This addendum changes the due date and time and clarifies the number of submittals.

Documents:

Posted: 9/17/2020

Type of Addition: In Review

Posted: 12/4/2020

Type of Addition: Award Information

Overview: Contracts have been awarded to the top five scoring firms in each category. Please see the memo excerpt attached.

Documents:

Posted: 8/18/2020

Question: 1. Please confirm that one proposal can be submitted for all three categories of scope of work. 2. As the proposals can be submitted electronically or mailed/hand delivered, will electronic submissions be printed for review or viewed online only?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 8/18/2020

Question: 3. Please confirm a consolidated financial statement is acceptable in lieu of an audited statement. 4. The last page of the Response Format section notes providing resumes for key staff members in one bullet and the following bullet notes providing resumes in the appendix, should all resumes be included in the appendix as opposed to the body of the document?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 8/21/2020

Question: What is the page limit for an electronic submittal? 50 or 100 pages?

Response: 50 pages front and back for submission of a physical copy; 100 pages electronically.

Posted: 8/24/2020

Question: Please provide a copy of the current Dorchester County CIP for reference.

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 8/25/2020

Question: Would you like one submittal for each category we are submitting on, or just one submittal total with combined qualifications?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 8/28/2020

Question: 6. Does DCWS have an existing water system model and if so, what hydraulic modeling software platform was used?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.

Posted: 8/28/2020

Question: In Section C, the RFQ asks for the following item: Current and projected workloads of the Firm. Please provide a summary document identifying the project data demonstrating the Firm’s ability to meet project time and budget requirements for up to the most recent 15 similar projects undertaken by the Firm Does the County wish us to provide 15 of our current and projected workload/projects per the first sentence? Or does the County wish us to provide 15 recent previous projects to capture our ability to meet time and budget requirements per the second sentence?

Response: This question is answered in Addendum 2 which will be posted today, 9/4.