Central Florida Expressway Authority Sealed Solicitation
Title: SR 417 POND MODIFICATIONS N. OF BERRY DEASE ROAD AND SR 528 WB TO SR 417 NB GUARDRAIL UPGRADES
Deadline: 9/16/2020 1:30 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 001725
Description:
The
work consists of providing all labor, materials, equipment and incidentals
necessary for the reconstruction of two roadside ponds and associated pipes,
drainage structures, riprap for ditch lining.
The work also includes guardrail replacement at two separate locations
and replacing electrical connections for roadway lighting.
Pre-Bid Meeting Date: 8/24/2020 11:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.Join Microsoft Teams Meeting +1 321-430-0870 United States, Orlando (Toll) Conference ID: 188 429 452#
Documents:
Documents as of 8/17/2020 |
---|
Login to view documents |
Login to view documents |
Login to view documents |
Login to view documents |
Addition 2
Posted: 8/24/2020
Type of Addition: Prebid Meeting Sign-in Sheet
Documents:
Addition 3
Posted: 9/1/2020
Type of Addition: Planholders List as of Sept 1. 2020 @ 1450
Solicitation #: 001725
Documents:
Addition 4
Posted: 9/14/2020
Type of Addition: Addendum No. 1
Overview:
This
Addendum forms a part of the Contract Documents and modifies the original bidding
documents dated August 2020, as noted below. Acknowledge receipt of this
Addendum in the space provided on the Proposal form. Failure to do so may
subject the bidder to disqualification. This
Addendum consists of 1 page.
Solicitation #: 001725
Documents:
Addition 5
Posted: 9/16/2020
Type of Addition: Bid Opening Minutes 001725
Overview: The Bid Opening for SR 417 Pond Modifications – North of Barry Dease Road & SR 528 And SR 417 Guardrail Upgrades; Project No. 417-162 (528-166); ITB-001725 was held at a duly noticed meeting on Wednesday, September 16, 2020, commencing at 1:30 p.m. at the Central Florida Expressway Authority Administrative Building, Orlando, Florida.
Documents:
Addition 6
Posted: 10/8/2020
Type of Addition: Bid Tabulation
Overview:
Documents:
Addition 7
Posted: 10/8/2020
Type of Addition: Award Information
Overview: Bids for this project were received and opened on September 16, 2020 at 1:30 p.m. The bid tabulation is attached hereto. On October 8, 2020 the CFX Board members awarded the Contract to the following firm, contingent upon final execution of the contract by both parties: Southern Development & Construction, Inc., 2544 Connection Point, Oviedo, Florida 32765 (Be sure to scroll down to view the Award Information located after Addition Note #6)
Amount: $1,047,740.00
Documents:
Posted: 9/1/2020
Type of Addition: Planholders List as of Sept 1. 2020 @ 1450
Solicitation #: 001725
Documents:
Posted: 9/14/2020
Type of Addition: Addendum No. 1
Overview:
This
Addendum forms a part of the Contract Documents and modifies the original bidding
documents dated August 2020, as noted below. Acknowledge receipt of this
Addendum in the space provided on the Proposal form. Failure to do so may
subject the bidder to disqualification. This
Addendum consists of 1 page.
Solicitation #: 001725
Documents:
Posted: 9/16/2020
Type of Addition: Bid Opening Minutes 001725
Overview: The Bid Opening for SR 417 Pond Modifications – North of Barry Dease Road & SR 528 And SR 417 Guardrail Upgrades; Project No. 417-162 (528-166); ITB-001725 was held at a duly noticed meeting on Wednesday, September 16, 2020, commencing at 1:30 p.m. at the Central Florida Expressway Authority Administrative Building, Orlando, Florida.
Documents:
Posted: 10/8/2020
Type of Addition: Award Information
Overview: Bids for this project were received and opened on September 16, 2020 at 1:30 p.m. The bid tabulation is attached hereto. On October 8, 2020 the CFX Board members awarded the Contract to the following firm, contingent upon final execution of the contract by both parties: Southern Development & Construction, Inc., 2544 Connection Point, Oviedo, Florida 32765 (Be sure to scroll down to view the Award Information located after Addition Note #6)
Amount: $1,047,740.00
Documents: