County of Beaufort Sealed Solicitation

Title: Burton Wells Pickleball Courts

Deadline: 12/2/2022 3:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: IFB 120222

Description: It is the intent of Beaufort County to solicit competitive sealed proposals from qualified and experienced
firms to provide construction services for the eight-court Pickleball facility at Burton Wells Recreation
Center in Beaufort County South Carolina

Please note the 2 attached Addendums are from the previously published IFB.


Pre-Bid Meeting Date: 11/17/2022 2:00 PM

Pre-Bid Meeting Details: A Pre-Bid meeting will be held virtually. Email victoria.moyer@bcgov.net to receive your invite.


Documents:

Documents as of 11/3/2022
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Addition 1

Posted: 11/8/2022

Type of Addition: Addendum #1

Overview: Please find Addendum 1 attached.

Documents:

Addition 2

Posted: 11/28/2022

Type of Addition: Addendum #2

Overview: Please see the attached Addendum #2 and Geotechnical Report

Documents:

Addition 3

Posted: 12/2/2022

Type of Addition: In Review

Addition 4

Posted: 12/5/2022

Type of Addition: Bid Tab

Overview: Please find the attached Bid Tab

Documents:

Addition 5

Posted: 2/21/2023

Type of Addition: Award Information

Overview: This was awarded to Wildwood Contractors Inc.

Amount: $609,488.00

Question 1

Posted: 11/7/2022

Question: Addendum #1 references alternates #1 - #4. These were previously included in IFB 013020E - Page 75. Will these alternates be taken for IFB 120222? Will an alternate form be provided?

Response: Please see the posted Addendum

Question 2

Posted: 11/7/2022

Question: Project Schedule: Please clarify. Invitation for Bid form (page 4) states "Unless otherwise stated and accepted herein, I agree to complete this proposed contract in less than One Hundred Sixty (160) calendar days after issue date of notice to proceed. Bid Form page 15 states "Contractor shall complete all work not later than 120 calendar days following the date of the Notice to Proceed or IAW any Special Provision by the Owner."

Response: The correct amount of time is One Hundred and Sixty (160).

Question 3

Posted: 11/17/2022

Question: The plans reference a geotechnical report, can you provide a copy of this report? Can you provide a spec/model for the court benches and shade shelter?

Response: Please see Addendum #2

Question 4

Posted: 11/21/2022

Question: Raingardens: the plans give a SF area of the raingardens and show the TOB at grade elevation 21 and BOB at a 20. The engineered soil is shown at grade elevation 19.25 which would be an additional 9 inches of cut from bottom of bank to install the engineered soil. On the raingarden detail shown on sheet #8, it specifies to install engineered soil 18" min, 36" preferred. For bidding purposes, can you specify a depth for engineered soil to be installed below bottom of bank?

Response: 18" depth

Question 5

Posted: 11/23/2022

Question: In regards to the Special Provisions Section 5A – Can you provide the location of “Supplemental Conditions, Section 104”? - Will a CAD copy to the plans be provided to the successful bidder?

Response: Please see Addendum #2

Posted: 11/8/2022

Type of Addition: Addendum #1

Overview: Please find Addendum 1 attached.

Documents:

Posted: 11/28/2022

Type of Addition: Addendum #2

Overview: Please see the attached Addendum #2 and Geotechnical Report

Documents:

Posted: 12/2/2022

Type of Addition: In Review

Posted: 12/5/2022

Type of Addition: Bid Tab

Overview: Please find the attached Bid Tab

Documents:

Posted: 2/21/2023

Type of Addition: Award Information

Overview: This was awarded to Wildwood Contractors Inc.

Amount: $609,488.00

Posted: 11/7/2022

Question: Addendum #1 references alternates #1 - #4. These were previously included in IFB 013020E - Page 75. Will these alternates be taken for IFB 120222? Will an alternate form be provided?

Response: Please see the posted Addendum

Posted: 11/7/2022

Question: Project Schedule: Please clarify. Invitation for Bid form (page 4) states "Unless otherwise stated and accepted herein, I agree to complete this proposed contract in less than One Hundred Sixty (160) calendar days after issue date of notice to proceed. Bid Form page 15 states "Contractor shall complete all work not later than 120 calendar days following the date of the Notice to Proceed or IAW any Special Provision by the Owner."

Response: The correct amount of time is One Hundred and Sixty (160).

Posted: 11/17/2022

Question: The plans reference a geotechnical report, can you provide a copy of this report? Can you provide a spec/model for the court benches and shade shelter?

Response: Please see Addendum #2

Posted: 11/21/2022

Question: Raingardens: the plans give a SF area of the raingardens and show the TOB at grade elevation 21 and BOB at a 20. The engineered soil is shown at grade elevation 19.25 which would be an additional 9 inches of cut from bottom of bank to install the engineered soil. On the raingarden detail shown on sheet #8, it specifies to install engineered soil 18" min, 36" preferred. For bidding purposes, can you specify a depth for engineered soil to be installed below bottom of bank?

Response: 18" depth

Posted: 11/23/2022

Question: In regards to the Special Provisions Section 5A – Can you provide the location of “Supplemental Conditions, Section 104”? - Will a CAD copy to the plans be provided to the successful bidder?

Response: Please see Addendum #2