Arlington County Government Sealed Solicitation
Title: 22-DES-ITB-405 Crane Inspection Services
Deadline: 9/28/2021 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Cancelled
Solicitation Number: 22-DES-ITB-405
Description:
For the provision of inspection, documentation, and routine preventative maintenance and repair services for material handling equipment at various county facilities.
Documents:
Documents as of 9/14/2021 |
---|
Updated 22-DES-ITB-405.pdf |
22-DES-ITB-405 Addendum 1.pdf |
Updated Attachment A - Pricing Sheet.xlsx |
Attachment B - Equipment List.xlsx |
Addition 1
Posted: 9/28/2021
Type of Addition: In Review
Addition 2
Posted: 10/8/2021
Type of Addition: Cancellation Information
Overview: All Bids Rejected
Documents:
Question 1
Posted: 9/7/2021
Question: There’s a section for equipment pricing, and a section that details hourly rates. I’ve broken out our quoted price into the equipment section. That price includes our hourly rates. As a result, when I enter the hourly rates, the total price practically doubles. Is that acceptable, or is there another way you would like us to break this out?
Response: The estimated quantities for hourly rates were based on the work required for Table A. These have been removed from the award formula. Bidders must still provide rates for the items in Table B for additional, urgent or emergency work, but they will not be included in the Method of Award. Please refer to Addendum 1, the Updated 22-DES-ITB-405 and the Updated Attachment A - Pricing Sheet.
Posted: 9/28/2021
Type of Addition: In Review
Posted: 10/8/2021
Type of Addition: Cancellation Information
Overview: All Bids Rejected
Documents:
Posted: 9/7/2021
Question: There’s a section for equipment pricing, and a section that details hourly rates. I’ve broken out our quoted price into the equipment section. That price includes our hourly rates. As a result, when I enter the hourly rates, the total price practically doubles. Is that acceptable, or is there another way you would like us to break this out?
Response: The estimated quantities for hourly rates were based on the work required for Table A. These have been removed from the award formula. Bidders must still provide rates for the items in Table B for additional, urgent or emergency work, but they will not be included in the Method of Award. Please refer to Addendum 1, the Updated 22-DES-ITB-405 and the Updated Attachment A - Pricing Sheet.