Arlington County Government Sealed Solicitation

Title: 20-269-7 -ITB, Project No. P26D - 18th Street, North Glebe Road, North Wakefild Street Intersection Improvements

Deadline: 8/7/2020 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Deadline Expired

Solicitation Number: 29-269-7ITB, Project No. P26D

Description: Streetscape Improvements at 18th Street, North Glebe Road, North Wakefield Street Intersections.


Documents:

Documents as of 7/9/2020
Solicitation 07-09-20.pdf
Section III-General Conditions 07-09-20.pdf
Sections IV, V, VI-Special Conditions, Supplemental Specifications, Insurance 07-09-20.pdf
Section VII-Attachments, Forms .pdf
Bid, Insurance Forms 09-09-18.pdf
Addition 1

Posted: 7/10/2020

Type of Addition: Addendum No. 1

Solicitation #: 20-269-7 Project No. P26D

Documents:

Addition 2

Posted: 7/10/2020

Type of Addition: Addendum No. 2

Overview:

Attachment F-1-Construction Drawings-18th Street

Attachment F-3-Drainage, Soil Map
 

Solicitation #: 20-269-7-ITB, Project No. P26d

Documents:

Addition 3

Posted: 7/13/2020

Type of Addition: Addendum No. 3

Overview:

Erosion Sediment Plan

Traffic Signal Drawings
 

Documents:

Addition 4

Posted: 7/17/2020

Type of Addition: Addendum No. 4

Overview: Change to Substantial Completion Date

Documents:

Question 1

Posted: 7/15/2020

Question: Traffic signal items for this project have long lead times that are now even longer during this pandemic. The ITB has included 160 calendar days for completion of this project which is not enough to procure the signal items. Will the County extend the completion time to at least 240 calendar days to allow sufficient time for procurement of these items?

Response:

Posted: 7/10/2020

Type of Addition: Addendum No. 1

Solicitation #: 20-269-7 Project No. P26D

Documents:

Posted: 7/10/2020

Type of Addition: Addendum No. 2

Overview:

Attachment F-1-Construction Drawings-18th Street

Attachment F-3-Drainage, Soil Map
 

Solicitation #: 20-269-7-ITB, Project No. P26d

Documents:

Posted: 7/13/2020

Type of Addition: Addendum No. 3

Overview:

Erosion Sediment Plan

Traffic Signal Drawings
 

Documents:

Posted: 7/17/2020

Type of Addition: Addendum No. 4

Overview: Change to Substantial Completion Date

Documents:

Posted: 7/15/2020

Question: Traffic signal items for this project have long lead times that are now even longer during this pandemic. The ITB has included 160 calendar days for completion of this project which is not enough to procure the signal items. Will the County extend the completion time to at least 240 calendar days to allow sufficient time for procurement of these items?

Response: