University of Alabama in Huntsville Sealed Solicitation
Title: Housing and Residence Life Cable Services
Deadline: 6/13/2018 1:30 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: P00115
Description: The University of Alabama in Huntsville is seeking proposals from qualified companies to provide quality high definition transitioning into IP cable television services for several of the University's housing and residence life buildings.
Pre-Bid Meeting Date: 6/6/2018 10:30 AM
Pre-Bid Meeting Details: This pre-bid conference will take place in the Housing and Residence Life building (Charger Village) from 10:30 until 12:30 pm.
Documents:
Documents as of 5/15/2018 |
---|
Revised Cable Proposal 5.15.2018.docx |
Addition 1
Posted: 6/8/2018
Type of Addition: Addendum
Overview: UAH has made a revision to P00115 UAH Housing Cable Services for the reasons stated in the addendum attached.
Documents:
Addition 2
Posted: 6/8/2018
Type of Addition: Addendum P00115.RV01
Overview: The University of Alabama has adjusted the Bid open date to allow time for the issues to be addressed as stated in the attached addendum.
Deadline: 6/13/2018 1:30 PM
Solicitation #: P00115.RV01
Documents:
Addition 3
Posted: 6/15/2018
Type of Addition: Award Information
Overview: UAH has awarded this proposal to Comcast based off of the criteria specified in the score card attached below.
Documents:
Question 1
Posted: 5/17/2018
Question: What is the term length for this contract?
Response: The initial term of the contract shall commence upon the date of its execution and shall continue for an initial term of five (5) years. This Agreement shall be automatically renewed for 5 successive one-year renewal periods unless terminated by either party giving the other party notice of termination in writing at least ninety (90) days in advance of the end of the initial or any renewal term. The compensation payable by Owner to Operator during any renewal period shall be the same as that payable during the initial term unless the parties shall agree to the contrary in writing in advance of that renewal.
Question 2
Posted: 5/17/2018
Question: Will a formal contract be negotiated after the RFP, or does the RFP response itself serve as the official contract? What is the process after award of RFP to fully execute a contract?
Response: The RFP will serve as the official contract.
Question 3
Posted: 5/17/2018
Question: Please confirm: do all RFP responses need to be submitted online via VendorRegistry, in person/via mail to the University as outlined on page 4 of the RFP, or by both delivery methods?
Response: All responses should be submitted via Vendor Registry. No responses will be accepted via mail or in person.
Question 4
Posted: 5/21/2018
Question: Does the existing CATV distribution system have a single point of insertion that facilitates CATV signal distribution to all the buildings receiving CATV signal on campus? If Yes, please identify this signal insertion location?
Response: Each building has its own insertion point.
Question 5
Posted: 5/21/2018
Question: Will the University provide system design prints of the existing CATV distribution system?
Response: No system design currently exists
Question 6
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution cable between buildings?
Response: Each building is currently seperate
Question 7
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution cable within buildings?
Response: No, just wiring.
Question 8
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution system electronics between buildings?
Response: There's no existing CATV Distribution system
Question 9
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution system electronics inside of the buildings?
Response: The University owns all wiring
Question 10
Posted: 5/21/2018
Question: Are non-residential buildings to be included in the scope of this project? If yes, please provide the names of all non-residential buildings that currently receive cable TV service and the number of coaxial service drops in each of these buildings?
Response: No, this is for residential life/housing buildings only
Question 11
Posted: 5/21/2018
Question: Please identify buildings served by the CATV system and the quantity of coaxial service drops to be served in each of these buildings.
Response: Same as above
Question 12
Posted: 5/21/2018
Question: Please identify buildings served by the CATV system and the quantity of units per building to be served.
Response: 2,733 outlets, in the manner described herein, Central Campus 523 outlets, Charger Village 537 outlets, Charger Village expansion 526 outlets, Frank Franz 316 outlets, Fraternity/Sorority 65 outlets, North Campus 375 outlets, and Southeast Campus 391. These numbers include the addition of service to the expansion of Charger Village.
Question 13
Posted: 5/23/2018
Question: Are vendors supposed to submit responses 1) in person/via mail with original version and hard copy, 2) electronically via Vendor Registry (as mentioned in Section 4.3), OR 3) through both delivery methods?
Response: Via Vendor Registry
Question 14
Posted: 6/4/2018
Question: The RFP states that the mandatory campus visit is Tuesday, June 6. Please confirm - is the meeting on Tuesday, 6/5 or Wednesday, 6/6?
Response: The Mandatory Campus Visit will take place on WEDNESDAY June 6, 2018.
Question 15
Posted: 6/5/2018
Question: What is meant by 4-T channels in Section 3.4 of the RFP?
Response: Interactive Channels, so that UAH can have our own channel(s) within the halls.
Question 16
Posted: 6/5/2018
Question: Does the University insert video content over their system today? If so, what type of content? Does the University intend to continue inserting content on individual channels moving forward?
Response: No, but plans to do so. Would be video, Power Point, information based.
Question 17
Posted: 6/7/2018
Question: Where is the head end for the portion of campus currently served by other incumbent provider on campus (not Comcast)?
Response: This is unknown as the present time
Question 18
Posted: 6/7/2018
Question: What is the deadline for activation of services for the vendor that is successfully awarded the bid?
Response: Linear- August 1, 2018, IPTV as listed in RFP
Question 19
Posted: 6/7/2018
Question: In Section 3.2, this requirement refers to all NEW cabling that the vendor may need to install to deliver services, correct?
Response: If it is RG^, any new wiring will need to be this or industry standard.
Question 20
Posted: 6/7/2018
Question: Are there any cable boxes in place to provide service today?
Response: No
Question 21
Posted: 6/7/2018
Question: Is there space for wall mounted 5x5 ft plywood board and power in a ventilated room/closet available in Charge Union Hall to install cable network equipment?
Response: Yes there is space available.
Question 22
Posted: 6/7/2018
Question: Is there conduit space available to pull fiber from the outside into Von Braun Research Building (Telco/Data Center demarc)?
Response: Yes, the East side is better
Question 23
Posted: 6/7/2018
Question: What type of content will the University want to insert into the IPTV channel lineup?
Response: Middle of the Road: Sports Local News HBO Family Discovery (Mandatory) Educational Basic (USA, TNT, FX, AMC, etc..._
Posted: 6/8/2018
Type of Addition: Addendum
Overview: UAH has made a revision to P00115 UAH Housing Cable Services for the reasons stated in the addendum attached.
Documents:
Posted: 6/8/2018
Type of Addition: Addendum P00115.RV01
Overview: The University of Alabama has adjusted the Bid open date to allow time for the issues to be addressed as stated in the attached addendum.
Deadline: 6/13/2018 1:30 PM
Solicitation #: P00115.RV01
Documents:
Posted: 6/15/2018
Type of Addition: Award Information
Overview: UAH has awarded this proposal to Comcast based off of the criteria specified in the score card attached below.
Documents:
Posted: 5/17/2018
Question: What is the term length for this contract?
Response: The initial term of the contract shall commence upon the date of its execution and shall continue for an initial term of five (5) years. This Agreement shall be automatically renewed for 5 successive one-year renewal periods unless terminated by either party giving the other party notice of termination in writing at least ninety (90) days in advance of the end of the initial or any renewal term. The compensation payable by Owner to Operator during any renewal period shall be the same as that payable during the initial term unless the parties shall agree to the contrary in writing in advance of that renewal.
Posted: 5/17/2018
Question: Will a formal contract be negotiated after the RFP, or does the RFP response itself serve as the official contract? What is the process after award of RFP to fully execute a contract?
Response: The RFP will serve as the official contract.
Posted: 5/17/2018
Question: Please confirm: do all RFP responses need to be submitted online via VendorRegistry, in person/via mail to the University as outlined on page 4 of the RFP, or by both delivery methods?
Response: All responses should be submitted via Vendor Registry. No responses will be accepted via mail or in person.
Posted: 5/21/2018
Question: Does the existing CATV distribution system have a single point of insertion that facilitates CATV signal distribution to all the buildings receiving CATV signal on campus? If Yes, please identify this signal insertion location?
Response: Each building has its own insertion point.
Posted: 5/21/2018
Question: Will the University provide system design prints of the existing CATV distribution system?
Response: No system design currently exists
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution cable between buildings?
Response: Each building is currently seperate
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution cable within buildings?
Response: No, just wiring.
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution system electronics between buildings?
Response: There's no existing CATV Distribution system
Posted: 5/21/2018
Question: Does the University own the existing CATV distribution system electronics inside of the buildings?
Response: The University owns all wiring
Posted: 5/21/2018
Question: Are non-residential buildings to be included in the scope of this project? If yes, please provide the names of all non-residential buildings that currently receive cable TV service and the number of coaxial service drops in each of these buildings?
Response: No, this is for residential life/housing buildings only
Posted: 5/21/2018
Question: Please identify buildings served by the CATV system and the quantity of coaxial service drops to be served in each of these buildings.
Response: Same as above
Posted: 5/21/2018
Question: Please identify buildings served by the CATV system and the quantity of units per building to be served.
Response: 2,733 outlets, in the manner described herein, Central Campus 523 outlets, Charger Village 537 outlets, Charger Village expansion 526 outlets, Frank Franz 316 outlets, Fraternity/Sorority 65 outlets, North Campus 375 outlets, and Southeast Campus 391. These numbers include the addition of service to the expansion of Charger Village.
Posted: 5/23/2018
Question: Are vendors supposed to submit responses 1) in person/via mail with original version and hard copy, 2) electronically via Vendor Registry (as mentioned in Section 4.3), OR 3) through both delivery methods?
Response: Via Vendor Registry
Posted: 6/4/2018
Question: The RFP states that the mandatory campus visit is Tuesday, June 6. Please confirm - is the meeting on Tuesday, 6/5 or Wednesday, 6/6?
Response: The Mandatory Campus Visit will take place on WEDNESDAY June 6, 2018.
Posted: 6/5/2018
Question: What is meant by 4-T channels in Section 3.4 of the RFP?
Response: Interactive Channels, so that UAH can have our own channel(s) within the halls.
Posted: 6/5/2018
Question: Does the University insert video content over their system today? If so, what type of content? Does the University intend to continue inserting content on individual channels moving forward?
Response: No, but plans to do so. Would be video, Power Point, information based.
Posted: 6/7/2018
Question: Where is the head end for the portion of campus currently served by other incumbent provider on campus (not Comcast)?
Response: This is unknown as the present time
Posted: 6/7/2018
Question: What is the deadline for activation of services for the vendor that is successfully awarded the bid?
Response: Linear- August 1, 2018, IPTV as listed in RFP
Posted: 6/7/2018
Question: In Section 3.2, this requirement refers to all NEW cabling that the vendor may need to install to deliver services, correct?
Response: If it is RG^, any new wiring will need to be this or industry standard.
Posted: 6/7/2018
Question: Are there any cable boxes in place to provide service today?
Response: No
Posted: 6/7/2018
Question: Is there space for wall mounted 5x5 ft plywood board and power in a ventilated room/closet available in Charge Union Hall to install cable network equipment?
Response: Yes there is space available.
Posted: 6/7/2018
Question: Is there conduit space available to pull fiber from the outside into Von Braun Research Building (Telco/Data Center demarc)?
Response: Yes, the East side is better
Posted: 6/7/2018
Question: What type of content will the University want to insert into the IPTV channel lineup?
Response: Middle of the Road: Sports Local News HBO Family Discovery (Mandatory) Educational Basic (USA, TNT, FX, AMC, etc..._