Town of Summerville Sealed Solicitation

Title: ITB - Bear Island Road Project

Deadline: 5/1/2019 11:30 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Deadline Expired

Description:

The work includes earthwork, grading, paving, and drainage facilities in order to construct and widen Bear Island Road and Old Light Road. The project also includes landscaping. The total estimated length of the project is total approximately roadway length of 1.4 miles.
A mandatory pre-bid conference will be held at 11:00 a.m. local time on Wednesday, April 10, 2019, in the 2nd floor Training Room, Summerville Town Hall Annex, 200 South Main Street, Summerville, South Carolina 29483. For final construction plans, please use the following link: 

https://eFTP.mbakerintl.com/message/5NCdT0dCxsigKXDdbVZM3b 


Pre-Bid Meeting Date: 4/10/2019 11:00 AM


Documents:

Documents as of 3/14/2019
BIR Bid Docs.pdf
Addition 1

Posted: 3/25/2019

Type of Addition: Addendum #1

Overview: Please copy and paste the following link into your browser. https://eftp.mbakerintl.com/message/o7GRaiMVesL2FXKGF26Y0Q

Addition 2

Posted: 4/12/2019

Type of Addition: Addendum

Overview: Pre-bid meeting sign-in sheet. (PDF attached)

Documents:

Addition 3

Posted: 4/22/2019

Type of Addition: Addendum #3

Overview:

Final construction plans: https://eFTP.mbakerintl.com/message/yB5EahPsR8ftM2DJPyq5qj 

Final bid docs and revised plan sheets: https://eFTP.mbakerintl.com/message/cAU785uN0iLyQFvokz8STK 

Addition 4

Posted: 4/24/2019

Type of Addition: Addendum #4

Overview: Additional Q&A

Documents:

Addition 5

Posted: 4/26/2019

Type of Addition: Addendum #5

Overview: Q&A

Documents:

Addition 6

Posted: 5/8/2019

Type of Addition: Certified Bid Tabulation

Overview:

Documents:

Posted: 3/25/2019

Type of Addition: Addendum #1

Overview: Please copy and paste the following link into your browser. https://eftp.mbakerintl.com/message/o7GRaiMVesL2FXKGF26Y0Q

Posted: 4/12/2019

Type of Addition: Addendum

Overview: Pre-bid meeting sign-in sheet. (PDF attached)

Documents:

Posted: 4/22/2019

Type of Addition: Addendum #3

Overview:

Final construction plans: https://eFTP.mbakerintl.com/message/yB5EahPsR8ftM2DJPyq5qj 

Final bid docs and revised plan sheets: https://eFTP.mbakerintl.com/message/cAU785uN0iLyQFvokz8STK 

Posted: 4/24/2019

Type of Addition: Addendum #4

Overview: Additional Q&A

Documents:

Posted: 4/26/2019

Type of Addition: Addendum #5

Overview: Q&A

Documents:

Posted: 5/8/2019

Type of Addition: Certified Bid Tabulation

Overview:

Documents: