County of Escambia Sealed Solicitation

Title: PD 22-23.012 Moreno Street Stormwater Pond and Sidewalks Improvements

Deadline: 12/9/2022 3:00 PM   (UTC-06:00) Central Time (US & Canada)

Status: Cancelled

Solicitation Number: PD 22-23.012

Description: The Moreno Street Stormwater Pond and Sidewalk Improvements project includes the construction of stormwater pond intended to help alleviate flooding at a low area north of Moreno Street between Q and R Streets. Presently, an existing drainage system terminates in this area with no developed outfall. New stormwater piping and inlets will be constructed upstream of the pond to help facilitate drainage into the pond. The pond will be constructed with a sand chimney and EGRP “Straws” to facilitate recovery.
The project also includes the construction of a sidewalk around the block made up of ‘Q’ and ‘R’ Streets to the east and west and Mallory and Moreno Streets to the north and south.


Pre-Bid Meeting Date: 11/17/2022 1:00 PM

Pre-Bid Meeting Details: Non-mandatory TEAMS meeting.


Documents:

Documents as of 11/3/2022
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Addition 1

Posted: 11/17/2022

Type of Addition: Pre Solicitation Attendance Sheet

Documents:

Addition 2

Posted: 11/21/2022

Type of Addition: Addendum 1

Overview: 1. Performance and Payment Bonds are required
2. Warranty is two years after final project completion
3. Retainage is 5% of gross billed amount
4. Supplemental Provisions for Construction are provided.

Documents:

Addition 3

Posted: 12/16/2022

Type of Addition: Replace Bid Tab Under Review Document

Overview:

Documents:

Addition 4

Posted: 1/31/2023

Type of Addition: Cancellation Information

Question 1

Posted: 11/16/2022

Question: Is a payment and performance bond required for this project? What is the retainage for this project? What is the warranty length for this project? This information is not stated in the solicitation.

Response: We have already responded to this question. Please see the public solicitation. Addendum 1

Posted: 11/17/2022

Type of Addition: Pre Solicitation Attendance Sheet

Documents:

Posted: 11/21/2022

Type of Addition: Addendum 1

Overview: 1. Performance and Payment Bonds are required
2. Warranty is two years after final project completion
3. Retainage is 5% of gross billed amount
4. Supplemental Provisions for Construction are provided.

Documents:

Posted: 12/16/2022

Type of Addition: Replace Bid Tab Under Review Document

Overview:

Documents:

Posted: 1/31/2023

Type of Addition: Cancellation Information

Posted: 11/16/2022

Question: Is a payment and performance bond required for this project? What is the retainage for this project? What is the warranty length for this project? This information is not stated in the solicitation.

Response: We have already responded to this question. Please see the public solicitation. Addendum 1