Clayton County Water Authority Sealed Solicitation
Title: W.J. Hooper Water Production Plant Chemical Storage Systems
Deadline: 1/17/2023 10:00 AM (UTC-05:00) Eastern Time (US & Canada)
Status: Deadline Expired
Solicitation Number: 2023-WP-01
Description: Separate sealed Bids for the construction of W.J. Hooper Water Production Plant Chemical Storage Systems will be received by the Clayton County Water Authority (CCWA) at 1600 Battle Creek Road, Morrow, Georgia 30260 until 10:00 a.m. local time, the 17th day of January 2023, and then at said office opened and read aloud. Any bids received after the specified time will not be considered. The bid opening conference will be hosted virtually as a conference call meeting.
Click here to join the meeting
or
Phone number: +1 912-483-5368
Conference ID: 142 001 630#
To join the bid opening conference call, use the Microsoft Teams link or below call-in number:
Click here to join the meeting
or
Phone number: +1 912-483-5368
Conference ID: 142 001 630#
As part of the effort to maintain the health and safety of CCWA personnel and its visitors, all participants will be required to conform to any COVID-19 protocols that may be in place at the time of the site visits and/or in person meetings. For security reasons, CCWA is also requiring the following procedures, practices, and protocols to be followed during the site visit:
A: Visitor(s) are required to sign the plant visitor’s log upon arrival to and departure from the plant.
C: Visitor(s) shall always be accompanied by a plant staff or Engineer while on-site.
The Project includes, but is not limited to, the following:
A: Supply and installation of two Sodium Hypochlorite storage tanks.
B: Supply and installation of Sulfuric Acid, Purate and Phosphoric Acid tanks.
C: Supply and installation of transfer pumping systems and appurtenances.
D: New chemical feed piping and tubing.
E: Tepid water supply and eyewash system.
F: Site modifications required to accommodate system and access thereof.
G: Demolition of existing storage tanks.
H: Demolition and replacement of storage area canopies
I: New instrumentation and control equipment as required.
The Bidding Documents, consisting of Advertisement for Competitive Sealed Bid, Instructions to Bidders, Bid Form, Bid Bond, Construction Contract, Performance Bond, Payment Bond, General and Supplementary Conditions, Specifications, Drawings, and Addenda may be examined at the main offices of the Owner at 1600 Battle Creek Road, Morrow, Georgia.
Copies of Bidding Documents are available at https://www.civcastusa.com for download and printing access. All Bidders are required to download a set of the Bidding Documents from the CIVCAST website. Bidders will be required to set up a CIVCAST account to access Bidding Documents including Addenda. Hard copies of Bidding Documents are the responsibility of the Bidders.
A list of planholders may be obtained by contacting James McCullough at James.McCullough@r2tinc.com.
CCWA encourages Small Local, Minority, and Women-Owned businesses to participate and respond to this bid request.
All questions related to the Project shall be submitted by email no later than 10:00 a.m., local time, on Monday, December 12, 2022 to James McCullough at James.McCullough@r2tinc.com. Questions, if answered, will be addressed by Addenda to the Contract Documents via the Q&A tab on the CIVCAST website for the project. Receipt of any Addenda or amendment to this Advertisement for Bids shall be acknowledged, in writing, and shall be submitted with the Bid.
Owner’s right is reserved to reject all Bids or any Bid not conforming to the intent and purpose of the Bidding Documents.
Pre-Bid Meeting Date: 12/8/2022 10:00 AM
Pre-Bid Meeting Details: There will be a MANDATORY Site Visit on Thursday, December 8, 2022 between 11 am - 2 pm at 70 Oakdale Drive, Stockbridge, GA 30281. Bidders shall schedule the Site Visit at least 24 hr in advance via email at James.McCullough@r2tinc.com or by phone at (678) 982-0789.
Documents:
Documents as of 1/10/2023 |
---|
WJ Hooper WPP Chemical Storage Systems - Addendum 1.pdf |
WJ Hooper WPP Chemical Storage Systems - Addendum 2.pdf |
Addition 1
Posted: 1/10/2023
Type of Addition: Addendum 1
Posted: 1/10/2023
Type of Addition: Addendum 1