Fox Valley Park District - Cole Center Administration Office Sealed Solicitation

Title: Gramercy Square Park

Deadline: 7/1/2025 11:00 AM   (UTC-06:00) Central Time (US & Canada)

Status: In Review

Solicitation Number: 060925JIC

Description: The scope of the work includes, but is not limited to, erosion control, grading, drainage, underground utility installation including storm sewers, and underdrains. The work also includes curb removal and replacement, asphalt and concrete paving, installation of playground curbing, sloped playground entry, playground equipment, engineered wood-fiber mulch, seeding and restoration.


Documents:

Documents as of 6/9/2025
Login to view documents
Login to view documents
Addition 1

Posted: 6/26/2025

Type of Addition: Addendum

Overview: UMMARY OF CHANGES

This addendum includes revision to Project Specifications for Section 11 68 00 Play Field Equipment and Structures.



REVISIONS TO PROJECT SPECIFICATIONS



SECTION 11 68 00

1.02 QUALITY ASSURANCE



DELETE Section B. Manufacturer Qualifications. Playground components will be provided by Owner for installation by Contractor.



END OF ADDENDUM

Deadline: 7/1/2025 11:00 AM

Documents:

Addition 2

Posted: 7/17/2025

Type of Addition: In Review

Addition 3

Posted: 7/17/2025

Type of Addition: Bid Tab

Overview: Bid Tabulation

Documents:

Question 1

Posted: 6/19/2025

Question: Will the park district be purchasing the playground equipment or will the contractor need to include the purchase of the equipment in their bid?

Response: FVPD will purchase the equipment, this question will be clarified in addendum 1.

Question 2

Posted: 6/20/2025

Question: Good morning, I would like to clarify Iif this project requires the installation of Kompan-Imagine Nation playground equipment as described on page 94 of the project manual. I see this equipment specified in the manual, but it does not appear in the plans. Could you please confirm whether it is included in the scope of work? Thank you for your assistance.

Response: This question is addressed in addendum 1.

Posted: 6/26/2025

Type of Addition: Addendum

Overview: UMMARY OF CHANGES

This addendum includes revision to Project Specifications for Section 11 68 00 Play Field Equipment and Structures.



REVISIONS TO PROJECT SPECIFICATIONS



SECTION 11 68 00

1.02 QUALITY ASSURANCE



DELETE Section B. Manufacturer Qualifications. Playground components will be provided by Owner for installation by Contractor.



END OF ADDENDUM

Deadline: 7/1/2025 11:00 AM

Documents:

Posted: 7/17/2025

Type of Addition: In Review

Posted: 7/17/2025

Type of Addition: Bid Tab

Overview: Bid Tabulation

Documents:

Posted: 6/19/2025

Question: Will the park district be purchasing the playground equipment or will the contractor need to include the purchase of the equipment in their bid?

Response: FVPD will purchase the equipment, this question will be clarified in addendum 1.

Posted: 6/20/2025

Question: Good morning, I would like to clarify Iif this project requires the installation of Kompan-Imagine Nation playground equipment as described on page 94 of the project manual. I see this equipment specified in the manual, but it does not appear in the plans. Could you please confirm whether it is included in the scope of work? Thank you for your assistance.

Response: This question is addressed in addendum 1.