Town of Bluffton Sealed Solicitation
Title: Buck Island Simmonsville sewer phase V cure REBID - IFB
Deadline: 4/17/2023 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 2023-55
Description: The Town of Bluffton is soliciting competitive sealed bids to complete a water and sewer installation cure project. The drawings and scope of work detail the required fixes and testing. This project is funded in part by a Community Development Block Grant; bidders must be aware that the 2023 Davis Bacon schedule included herein will be applicable, that a bid-holders list will be documented, and that terms and conditions of the grant will apply. See all attachments.
Pre-Bid Meeting Date: 3/22/2023 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting. Meeting is non-mandatory and virtual via Teams. See solicitation for link. Please log into Vendor Registry to sign in as well.
Documents:
PLANHOLDERS:
Date | Company Name |
---|---|
3/14/2023 12:10:38 PM | R. H. Moore Company, Inc. |
3/14/2023 1:48:46 PM | Quality Enterprises USA, Inc. |
3/14/2023 2:03:54 PM | Sandhill ALS Construction Inc |
3/15/2023 1:53:11 PM | ConstructionBid Source |
3/15/2023 3:49:02 PM | Dodge Data & Analytics |
3/16/2023 6:21:39 AM | Garney Companies, inc |
3/16/2023 11:11:32 AM | Metra Industries |
3/17/2023 8:19:47 AM | Morgan Contracting, Inc. |
3/18/2023 6:10:35 AM | Civil Solutions |
3/21/2023 9:23:28 PM | AG Ltd |
3/22/2023 3:31:48 AM | Dodge Data |
3/22/2023 3:31:09 PM | Inliner Solutions, LLC |
3/22/2023 3:41:25 PM | Cleary Construction, Inc. |
3/23/2023 2:36:21 AM | Dodge Data & Analytics |
3/28/2023 8:39:23 AM | Insituform Technologies, LLC |
4/3/2023 7:55:44 AM | CBG Inc. |
4/3/2023 8:32:45 AM | Sturre Design & Development, LLC |
4/10/2023 3:45:22 PM | Jordan Construction of Hilton Head, Inc. |
4/13/2023 9:46:15 AM | Potter Construction, LLC |
4/19/2023 1:42:03 PM | ConstructConnect |
6/2/2023 3:39:25 PM | Lowcountry Council of Governments |
11/3/2023 8:24:14 AM | J S Construction Services, Inc. |
1/15/2024 3:17:28 PM | CBG, Inc. |
2/20/2024 1:57:46 AM | PWXPress |
7/30/2024 5:01:41 AM | Dodge Data & Analytics |
10/3/2024 3:54:02 AM | Deltek |
Addition 1
Posted: 3/21/2023
Type of Addition: Addendum 1
Overview: Extends time to submit bids.
Deadline: 4/17/2023 2:00 PM
Documents:
Question 1
Posted: 3/29/2023
Question: Good morning...one last question... After you receive bids, and if one is acceptable, when do you anticipate a start date for this project? Thanks
Response: This project must be approved by Town Council and by the Department of Commerce but we are looking at expedited timelines such as the May Town Council meeting and seeking Commerce approval simultaneously.
Posted: 3/21/2023
Type of Addition: Addendum 1
Overview: Extends time to submit bids.
Deadline: 4/17/2023 2:00 PM
Documents:
Posted: 3/29/2023
Question: Good morning...one last question... After you receive bids, and if one is acceptable, when do you anticipate a start date for this project? Thanks
Response: This project must be approved by Town Council and by the Department of Commerce but we are looking at expedited timelines such as the May Town Council meeting and seeking Commerce approval simultaneously.