County of Escambia Sealed Solicitation
Title: PD 21-22.039 Beulah Fire Station Construction
Deadline: 4/6/2022 4:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: PD 21-22.039
Description: The Work generally consists of, but is not limited to, the construction of a new 14,503 GSF fire station and associated site work. The foundations and floor slab will be poured in place concrete. The exterior walls will be insulated concrete formwork with brick veneer. The roof system will be structural steel framing, two types of metal decking, rigid roof insulation and standing seam steel roof. Interior walls will be either painted concrete masonry units or painted gypsum board on steel studs. The floor finish is either sealed concrete, monolithic poured epoxy, or carpet tiles. Finish ceilings will be either suspended acoustical ceiling tiles or exposed metal deck. Apparatus bay doors will be both four-fold high speed and coiling overhead doors. The HVAC is split system heat pump units. The apparatus bays have radiant gas heat. Plumbing is standard porcelain fixtures and institutional grade piping. Electrical is standard institution grade LED lighting and power distribution. The facility will have access control system, public address and speakers, MACH alerting and radio system. Civil site includes both concrete and asphalt pavements. Other civil work includes grading, stormwater treatment, landscaping and other associated work. A traffic control signal system on strain wire and concrete poles at Nine Mile Road is included.
Pre-Bid Meeting Date: 3/15/2022 10:00 AM
Pre-Bid Meeting Details: Non=mandatory Meeting
Documents:
Documents as of 3/1/2022 |
---|
Login to view documents |
Login to view documents |
Login to view documents |
Login to view documents |
Addition 1
Posted: 3/15/2022
Type of Addition: Addendum 1
Overview: Site Visit
Documents:
Addition 2
Posted: 3/16/2022
Type of Addition: Addendum 2
Overview: Bid Due Date extended to April 6, 2022 , 4:00 PM CT.
Deadline: 4/6/2022 4:00 PM
Solicitation #: PD 21-22.039
Documents:
Addition 3
Posted: 3/18/2022
Type of Addition: Addendum 3
Overview: 1. Attendance list from 3/17/22 Site Visit
Documents:
Addition 4
Posted: 3/22/2022
Type of Addition: Addendum 4
Overview: Addendum #4 - Response to Question Set #1 and #2
Documents:
Addition 5
Posted: 3/22/2022
Type of Addition: Addition
Overview: Site Visit Attendance Sheet
Documents:
Addition 6
Posted: 3/24/2022
Type of Addition: Addendum 5
Overview: Revision of Partial Payment Process.
Documents:
Addition 7
Posted: 3/25/2022
Type of Addition: Addendum 6
Overview: Responses to Bidder provided questions
b. 012100-ALLOWANCES1
c. 017320-SELECTIVE DEMOLITION1
d. 028100-STRUCTURE DEMOLITION1
e. 033000-Cast-In-Place Concrete REVISED 3-25-22
f. 096813 - TILE CARPETING1
g. 20220325 - Fire Stations - Premier Rev
h. A401 WALL TYPES & SCHEDULES
i. Beulah FS sheet pile pond wall SK-1 3-25-2022
j. C-808 Details
k. Generator and Fuel Tank Pad Detail
l. Updated Construction Plans (C-402_C-403_C-404)
Documents:
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
Addition 8
Posted: 3/28/2022
Type of Addition: Addendum 7
Overview: Privice the Hazmat Survey Final Report.
Documents:
Addition 9
Posted: 3/29/2022
Type of Addition: Addendum 8
Overview: Provide the following forms:
2. Disclosure of Lobbying Activities
Documents:
Addition 10
Posted: 3/29/2022
Type of Addition: Addendum 9
Overview: Addendum 9
Documents:
Addition 11
Posted: 3/31/2022
Type of Addition: Addendum 10
Overview: Revised Invitation to Bid Rev A
Documents:
Addition 12
Posted: 4/7/2022
Type of Addition: In Review
Addition 13
Posted: 4/8/2022
Type of Addition: Project Under Review
Overview:
Documents:
Addition 14
Posted: 2/15/2023
Type of Addition: Award Information
Question 1
Posted: 3/1/2022
Question: There appears to be an issue with the “PD 21-22.039 Beulah FS Permit Set Plans.pdf” file uploaded to the County’s site. I believe the file is corrupt and therefore will not open. Can you please remove and replace the file?
Response: File has been replaced.
Question 2
Posted: 3/1/2022
Question: I am unable to open the plans. The file appears to be corrupt. Would you please upload them again?
Response: File has been replaced.
Question 3
Posted: 3/1/2022
Question: Regarding Local Preference in Bidding, please confirm if there are any outside funding sources, grants, etc. or any other factors that would exclude the use of local preference for this project.
Response: No outside funding.
Question 4
Posted: 3/2/2022
Question: It appears sheets C809 ad C810 were distorted when converted to PDF. Please provide replacement sheets.
Response: Provided with Addendum #4
Question 5
Posted: 3/2/2022
Question: Is there an estimated cost or budget?
Response: Provided in Addendum 4
Question 6
Posted: 3/5/2022
Question: In order to submit a bond request we will need to know the anticipated budget for this project. Please provide that cost.
Response: Provided in Addendum 4
Question 7
Posted: 3/22/2022
Question: Please advise on the county's anticipated budget for this project.
Response: See Addendum #4
Posted: 3/15/2022
Type of Addition: Addendum 1
Overview: Site Visit
Documents:
Posted: 3/16/2022
Type of Addition: Addendum 2
Overview: Bid Due Date extended to April 6, 2022 , 4:00 PM CT.
Deadline: 4/6/2022 4:00 PM
Solicitation #: PD 21-22.039
Documents:
Posted: 3/18/2022
Type of Addition: Addendum 3
Overview: 1. Attendance list from 3/17/22 Site Visit
Documents:
Posted: 3/22/2022
Type of Addition: Addendum 4
Overview: Addendum #4 - Response to Question Set #1 and #2
Documents:
Posted: 3/22/2022
Type of Addition: Addition
Overview: Site Visit Attendance Sheet
Documents:
Posted: 3/24/2022
Type of Addition: Addendum 5
Overview: Revision of Partial Payment Process.
Documents:
Posted: 3/25/2022
Type of Addition: Addendum 6
Overview: Responses to Bidder provided questions
b. 012100-ALLOWANCES1
c. 017320-SELECTIVE DEMOLITION1
d. 028100-STRUCTURE DEMOLITION1
e. 033000-Cast-In-Place Concrete REVISED 3-25-22
f. 096813 - TILE CARPETING1
g. 20220325 - Fire Stations - Premier Rev
h. A401 WALL TYPES & SCHEDULES
i. Beulah FS sheet pile pond wall SK-1 3-25-2022
j. C-808 Details
k. Generator and Fuel Tank Pad Detail
l. Updated Construction Plans (C-402_C-403_C-404)
Documents:
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
- Login to view documents
Posted: 3/28/2022
Type of Addition: Addendum 7
Overview: Privice the Hazmat Survey Final Report.
Documents:
Posted: 3/29/2022
Type of Addition: Addendum 8
Overview: Provide the following forms:
2. Disclosure of Lobbying Activities
Documents:
Posted: 3/29/2022
Type of Addition: Addendum 9
Overview: Addendum 9
Documents:
Posted: 3/31/2022
Type of Addition: Addendum 10
Overview: Revised Invitation to Bid Rev A
Documents:
Posted: 4/7/2022
Type of Addition: In Review
Posted: 4/8/2022
Type of Addition: Project Under Review
Overview:
Documents:
Posted: 2/15/2023
Type of Addition: Award Information
Posted: 3/1/2022
Question: There appears to be an issue with the “PD 21-22.039 Beulah FS Permit Set Plans.pdf” file uploaded to the County’s site. I believe the file is corrupt and therefore will not open. Can you please remove and replace the file?
Response: File has been replaced.
Posted: 3/1/2022
Question: I am unable to open the plans. The file appears to be corrupt. Would you please upload them again?
Response: File has been replaced.
Posted: 3/1/2022
Question: Regarding Local Preference in Bidding, please confirm if there are any outside funding sources, grants, etc. or any other factors that would exclude the use of local preference for this project.
Response: No outside funding.
Posted: 3/2/2022
Question: It appears sheets C809 ad C810 were distorted when converted to PDF. Please provide replacement sheets.
Response: Provided with Addendum #4
Posted: 3/2/2022
Question: Is there an estimated cost or budget?
Response: Provided in Addendum 4
Posted: 3/5/2022
Question: In order to submit a bond request we will need to know the anticipated budget for this project. Please provide that cost.
Response: Provided in Addendum 4
Posted: 3/22/2022
Question: Please advise on the county's anticipated budget for this project.
Response: See Addendum #4