Hazelwood School District Sealed Solicitation
Title: Boiler Replacement for HEHS
Deadline: 3/15/2021 10:00 AM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: 20_21-008 Boiler Replacement for HEHS
Description: Seeking bids for the replacement of the boilers at Hazelwood East High School
Pre-Bid Meeting Date: 3/10/2021 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.This is a MANDATORY Pre-Bid Meeting and it will be held at Hazelwood East High School at the address below: 11300 Dunn Road St. Louis, MO 63138
Documents:
Documents as of 3/5/2021 |
---|
Login to view documents |
Login to view documents |
Addition 1
Posted: 3/11/2021
Type of Addition: Addendum #1
Overview: Answer question of a potential proposer.
Deadline: 3/15/2021 10:00 AM
Solicitation #: 20_21-008 Boiler Replacement for HEHS
Documents:
Addition 2
Posted: 3/11/2021
Type of Addition: Addendum #2
Overview: REVISED BID SPECIFICATIONS
Deadline: 3/15/2021 10:00 AM
Solicitation #: 20_21-008 Boiler Replacement for HEHS
Documents:
Addition 3
Posted: 3/24/2021
Type of Addition: Award Information
Overview: Boilers Replacement for HEHS awarded to Murphy Co per Board Meeting held March 16, 2021
Documents:
Question 1
Posted: 3/11/2021
Question: Is the system pump, expansion tank, and air separator replacement included in this project?
Response: Please see Additions 1 & 2 that will answer your questions.
Posted: 3/11/2021
Type of Addition: Addendum #1
Overview: Answer question of a potential proposer.
Deadline: 3/15/2021 10:00 AM
Solicitation #: 20_21-008 Boiler Replacement for HEHS
Documents:
Posted: 3/11/2021
Type of Addition: Addendum #2
Overview: REVISED BID SPECIFICATIONS
Deadline: 3/15/2021 10:00 AM
Solicitation #: 20_21-008 Boiler Replacement for HEHS
Documents:
Posted: 3/24/2021
Type of Addition: Award Information
Overview: Boilers Replacement for HEHS awarded to Murphy Co per Board Meeting held March 16, 2021
Documents:
Posted: 3/11/2021
Question: Is the system pump, expansion tank, and air separator replacement included in this project?
Response: Please see Additions 1 & 2 that will answer your questions.