City of Woodstock Sealed Solicitation

Title: RFB 2025 - 05 Buckhead Crossing Trail Project

Deadline: 4/8/2025 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Deadline Expired

Solicitation Number: 2025 - 05

Description: The City of Woodstock, Georgia, herein referred to as the City, is accepting bids from qualified
contractors for the purpose of connecting the Towne Lake Pass trail to Towne Lake Pkwy at the
Buckhead Crossing intersection. This includes but is not limited to concrete sidewalk, a
pedestrian crosswalk, wheelchair ramps, steel handrails, a structural steel bridge install, and
guardrails at locations indicated in the plan set, hereinafter referred to as the “Project”.


Pre-Bid Meeting Date: 3/10/2025 10:00 AM

Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting. A pre-bid conference / site visit (mandatory) for all bidders will be held near the job site at 1460 Towne Lake Pkwy, Woodstock, GA 30189 on Monday, March 10th at 10 am.


Documents:

Documents as of 2/20/2025
Login to view documents
Login to view documents
Login to view documents

PLANHOLDERS:

Date Company Name
2/20/2025 11:34:25 AM Sol Construction LLC
2/20/2025 11:42:58 AM Woodwind Construction Company, Inc.
2/20/2025 11:50:56 AM JHC Corporation
2/20/2025 3:47:44 PM Surfaces Group
2/21/2025 9:59:16 AM ProLogic ITS, LLC
2/24/2025 9:36:05 AM BARTOW PAVING COMPANY, INC.
2/24/2025 10:46:23 AM Wilson Construction Management
2/25/2025 10:17:52 AM Black Diamond Designs Inc
2/25/2025 1:29:45 PM MC Squared LLC
2/26/2025 6:47:44 AM Baldwin Paving Company, Inc.
2/26/2025 10:02:58 AM NGT Group LLC
3/1/2025 2:51:30 PM Roadwize LLC
3/1/2025 3:17:25 PM Ohmshiv constructions LLC
3/2/2025 9:33:06 PM Na
3/4/2025 11:51:39 AM polivka international co inc.
3/5/2025 11:59:03 AM Carroll Daniel Construction Company
3/6/2025 11:02:04 AM BackBone Infrastructure, LLC
3/7/2025 11:16:04 AM Ryde Grading, Inc.
3/8/2025 10:27:07 AM Azimuth Contractors LLC
3/10/2025 8:05:06 AM North Georgia Concrete, Inc.
3/10/2025 9:30:34 AM Advanced Systems Inc
3/10/2025 4:50:39 PM R&B Developer, Inc
3/11/2025 1:07:50 PM J.G. Leone Enterprises, Inc
3/11/2025 1:08:00 PM Valmont
3/11/2025 1:10:59 PM Magnum Contracting, LLC
3/11/2025 1:24:14 PM Advanced Road Construction, LLC
3/12/2025 9:53:41 AM Miller Landscape, Inc.
3/12/2025 10:43:23 AM IP CONSTRUCTION, LLC
3/14/2025 9:54:40 AM New Life Landscapes
3/18/2025 3:37:39 PM R J Haynie & Associates
3/26/2025 10:12:59 AM Lagniappe Development Co, Inc.
3/27/2025 10:43:08 AM Southern States Grading
3/28/2025 7:47:42 AM Reynolds Fence & Guardrail, Inc.
3/31/2025 8:40:47 AM A1 Signs Inc
4/3/2025 12:26:41 PM Seacoast Construction Supply LLC
4/3/2025 2:01:58 PM Strack, Inc
4/3/2025 2:05:28 PM Strack, Inc.
4/3/2025 2:45:20 PM Vertical Earth Inc
4/3/2025 5:25:49 PM Axis Companies
4/3/2025 5:36:51 PM Dodge Data
4/3/2025 7:17:04 PM Lagniappe Development Co., Inc.
4/3/2025 9:18:35 PM AG Ltd
4/4/2025 8:19:11 AM ConstructConnect
4/7/2025 5:48:46 AM Deltek
4/7/2025 7:53:52 AM Dodge Data & Analytics
4/7/2025 10:27:43 AM GTG Traffic Signals
4/7/2025 12:03:16 PM Bridge Brothers
4/7/2025 3:49:41 PM north cherokee electrical
4/7/2025 7:10:45 PM Hasbun Construction
4/7/2025 10:17:13 PM Vertical Earth, Inc.
4/8/2025 8:45:08 AM FS Scarbrough LLC
4/8/2025 1:56:52 PM Access Alabama
Addition 1

Posted: 3/3/2025

Type of Addition: Addendum 1 - Pay Item Questions

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025 - 05

Documents:

Addition 2

Posted: 3/7/2025

Type of Addition: Addendum 2 - Updated Plan Set/Additional Documents

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025-05

Documents:

Addition 3

Posted: 3/14/2025

Type of Addition: Mandatory Pre-bid Sign In Sheet

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025-05

Documents:

Addition 4

Posted: 4/3/2025

Type of Addition: Addendum

Overview: Responses to Submitted Questions

New Pricing Sheet
Go To Meeting Bid Opening Link 
Bid Delayed until Tuesday, April 8th at 2:00 pm 

Deadline: 4/8/2025 2:00 PM

Solicitation #: 2025 - 05

Documents:

Question 1

Posted: 2/21/2025

Question: There is not a pay item for the 6" Concrete pavement walkway, can this be added?

Response: Question Received - See Addendum 1 Posting

Question 2

Posted: 2/21/2025

Question: There is not a pay item for the Concrete stairs, can this be added?

Response: Question Received - See Addendum 1 Posting

Question 3

Posted: 2/21/2025

Question: There is not a pay item for the handrail on the stairs, can this be added?

Response: Question Received - See Addendum 1 Posting

Question 4

Posted: 3/5/2025

Question: Will the owner/engineer please provide the CAD files for this project?

Response: Requested

Question 5

Posted: 3/5/2025

Question: The Q&A refers to a sealed addendum set with 10 additional pages. This does not appear to be located on the main documents page. Will and addendum be issued with the additional plans pages?

Response: Uploading now

Question 6

Posted: 3/7/2025

Question: Can the CAD be made available for earthwork modeling purposes?

Response: The CAD file will be made available to the awarded bidder.

Question 7

Posted: 3/12/2025

Question: is the bridge deck precast or poured in a pan?

Response: Poured in a pan

Question 8

Posted: 3/14/2025

Question: Can you post the pre-bid attendee list?

Response: Posted

Question 9

Posted: 3/24/2025

Question: Is a GC license required to submit a bid on this project?

Response: Response posted on addendum

Question 10

Posted: 3/24/2025

Question: Will the existing trail be closed during construction?

Response: Response posted on addendum

Question 11

Posted: 3/24/2025

Question: Can u-turns on Towne Lake Parkway at Buckhead Crossing be disallowed during construction?

Response: Response posted on addendum

Question 12

Posted: 3/24/2025

Question: Will the owner please provide a Profile of existing concrete trail on south side of creek (thickness, reinforcing etc)

Response: Response posted on addendum

Question 13

Posted: 3/24/2025

Question: Can an alternate item for beam material be submitted in lieu of Valmont?

Response: Response posted on addendum

Question 14

Posted: 3/24/2025

Question: Will the owner/engineer add a rock disposal pay item for rock encountered during construction of the trail?

Response: Response posted on addendum

Question 15

Posted: 3/24/2025

Question: Sheet 25-0002 notes number 5 states a ¾” conduit with #8 wire to each lighting standard, but note 6 is calling for 4- 2” conduits run under bridge? Which is correct? Can you please clarify this note?

Response: Response posted on addendum

Question 16

Posted: 3/24/2025

Question: 25-0002 states conduit as EMT, typically conduit below grade should be PVC, EMT can be used but is not common in this scenario. Can you please clarify conduit to be used both above and below grade?

Response: Response posted on addendum

Question 17

Posted: 3/24/2025

Question: Plans call for 11 lighting fixtures, and one blue tower security on sheet 25-0002, however, there does not appear to be a pay item for this. Can you please clarify how these will be paid out?

Response: Response posted on addendum

Question 18

Posted: 3/24/2025

Question: Regarding item, 631-5150 CMS Controller (Changeable message sign), where are these located? They do not appear to be called out on the plan set.

Response: Response posted on addendum

Question 19

Posted: 3/24/2025

Question: Regarding bid item 647-6057 Pedestal Pole, where are these located, they do not appear to be called out in the electrical plans?

Response: Response posted on addendum

Question 20

Posted: 3/24/2025

Question: Regarding bid item 647-6058 Pedestal Post, where are these located, they do not appear to be called out in the electrical plans?

Response: Response posted on addendum

Question 21

Posted: 3/24/2025

Question: Regarding bid item 682-2150 TP type 3 Pull box, signal plan calls for only one type 2 Pull Box. Where are the TP type 3 pull boxes located?

Response: Response posted on addendum

Question 22

Posted: 3/24/2025

Question: Regarding bid item 682-6222 Conduit NM (PVC) 500’, where is this to be used?

Response: Response posted on addendum

Question 23

Posted: 3/24/2025

Question: Regarding bid item 937-4000 Inductance loop, please confirm there is only one inductance loop to be installed.

Response: Response posted on addendum

Question 24

Posted: 3/24/2025

Question: Can a guardrail removal/replace bid item/pay item be added?

Response: Response posted on addendum

Question 25

Posted: 3/24/2025

Question: Are we permitted to do clearing/pruning (minimal) along Town Lake Hills Drive for access?

Response: Response posted on addendum

Question 26

Posted: 3/24/2025

Question: Will the owner/engineer please provide Load bearing capabilities of the boardwalk on south side of creek?

Response: Response posted on addendum

Posted: 3/3/2025

Type of Addition: Addendum 1 - Pay Item Questions

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025 - 05

Documents:

Posted: 3/7/2025

Type of Addition: Addendum 2 - Updated Plan Set/Additional Documents

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025-05

Documents:

Posted: 3/14/2025

Type of Addition: Mandatory Pre-bid Sign In Sheet

Deadline: 4/8/2025 10:00 AM

Solicitation #: 2025-05

Documents:

Posted: 4/3/2025

Type of Addition: Addendum

Overview: Responses to Submitted Questions

New Pricing Sheet
Go To Meeting Bid Opening Link 
Bid Delayed until Tuesday, April 8th at 2:00 pm 

Deadline: 4/8/2025 2:00 PM

Solicitation #: 2025 - 05

Documents:

Posted: 2/21/2025

Question: There is not a pay item for the 6" Concrete pavement walkway, can this be added?

Response: Question Received - See Addendum 1 Posting

Posted: 2/21/2025

Question: There is not a pay item for the Concrete stairs, can this be added?

Response: Question Received - See Addendum 1 Posting

Posted: 2/21/2025

Question: There is not a pay item for the handrail on the stairs, can this be added?

Response: Question Received - See Addendum 1 Posting

Posted: 3/5/2025

Question: Will the owner/engineer please provide the CAD files for this project?

Response: Requested

Posted: 3/5/2025

Question: The Q&A refers to a sealed addendum set with 10 additional pages. This does not appear to be located on the main documents page. Will and addendum be issued with the additional plans pages?

Response: Uploading now

Posted: 3/7/2025

Question: Can the CAD be made available for earthwork modeling purposes?

Response: The CAD file will be made available to the awarded bidder.

Posted: 3/12/2025

Question: is the bridge deck precast or poured in a pan?

Response: Poured in a pan

Posted: 3/14/2025

Question: Can you post the pre-bid attendee list?

Response: Posted

Posted: 3/24/2025

Question: Is a GC license required to submit a bid on this project?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Will the existing trail be closed during construction?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Can u-turns on Towne Lake Parkway at Buckhead Crossing be disallowed during construction?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Will the owner please provide a Profile of existing concrete trail on south side of creek (thickness, reinforcing etc)

Response: Response posted on addendum

Posted: 3/24/2025

Question: Can an alternate item for beam material be submitted in lieu of Valmont?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Will the owner/engineer add a rock disposal pay item for rock encountered during construction of the trail?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Sheet 25-0002 notes number 5 states a ¾” conduit with #8 wire to each lighting standard, but note 6 is calling for 4- 2” conduits run under bridge? Which is correct? Can you please clarify this note?

Response: Response posted on addendum

Posted: 3/24/2025

Question: 25-0002 states conduit as EMT, typically conduit below grade should be PVC, EMT can be used but is not common in this scenario. Can you please clarify conduit to be used both above and below grade?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Plans call for 11 lighting fixtures, and one blue tower security on sheet 25-0002, however, there does not appear to be a pay item for this. Can you please clarify how these will be paid out?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding item, 631-5150 CMS Controller (Changeable message sign), where are these located? They do not appear to be called out on the plan set.

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding bid item 647-6057 Pedestal Pole, where are these located, they do not appear to be called out in the electrical plans?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding bid item 647-6058 Pedestal Post, where are these located, they do not appear to be called out in the electrical plans?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding bid item 682-2150 TP type 3 Pull box, signal plan calls for only one type 2 Pull Box. Where are the TP type 3 pull boxes located?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding bid item 682-6222 Conduit NM (PVC) 500’, where is this to be used?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Regarding bid item 937-4000 Inductance loop, please confirm there is only one inductance loop to be installed.

Response: Response posted on addendum

Posted: 3/24/2025

Question: Can a guardrail removal/replace bid item/pay item be added?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Are we permitted to do clearing/pruning (minimal) along Town Lake Hills Drive for access?

Response: Response posted on addendum

Posted: 3/24/2025

Question: Will the owner/engineer please provide Load bearing capabilities of the boardwalk on south side of creek?

Response: Response posted on addendum