Whitfield County Schools Sealed Solicitation

Title: Technology - Access Control System for new North Whitfield Middle School

Deadline: 5/8/2020 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Cancelled

Solicitation Number: WCS-IT-2020-003-3

Description: Provide hardware, software and installation for Access Control system for our new North Whitfield Middle School


Documents:

Documents as of 4/7/2020
WCS-IT-2020-003-3.pdf
Question 1

Posted: 4/20/2020

Question: Can this work be done over the summer while students are out of school?

Response: This is a new building. No students present.

Question 2

Posted: 4/20/2020

Question: Training- What is required for this project? How many attendees and hours?

Response: There should only need to be training if you are offering something other than S2 and AiPhone. If you propose a different system, then you specify what training you would offer.

Question 3

Posted: 4/20/2020

Question: Is WCSD providing the Aiphone Programming?

Response: No, we will assist with IP, VLan and network information needed to configure and setup the system, but you will need to provide the install.

Question 4

Posted: 4/20/2020

Question: Is WCSD providing the S2 Programming?

Response: No, we will assist with IP, VLan and network information needed to configure and setup the system, but you will need to provide the install.

Question 5

Posted: 4/20/2020

Question: Is there an existing Access control system at this site? If yes is demo required and please provide exactly what devices would need to demo.

Response: This is a new building

Question 6

Posted: 4/20/2020

Question: Is this project New Construction or an existing site?

Response: New Construction

Question 7

Posted: 4/20/2020

Question: Does your existing main S2 controller have any spare capacity in it? If so how many spare licenses are there? Do we need to provide any S2 licensing for this project? If so how many licenses?

Response: No existing system

Question 8

Posted: 4/20/2020

Question: Is there any conduit work that will be required for this installation? If so can you please elaborate on exact locations and approximate footages? a. Can you please provide us the estimated number of Wall Penetrations/Fire wall penetrations that would be needed for this project? b. Will there be any MDF / IDF Wall Penetrations or sleeves needed for this project? c. Will be there by any Conduit at Door locations needed for this project? If yes how many doors would require it & would this need to be provided by us or others?

Response: All penetrations are covered under Electrical Contractor.

Question 9

Posted: 4/20/2020

Question: Will the site require a lift? If so can you please provide us with the type of lift (Size) that would work? Or if it is easier can you please provide us with the ceiling heights of areas that will require a lift?

Response: Assume you will need a lift in your quote. If if your responsibility to determine what lift is needed. We will add a drawing with MDF/IDF marked as well as a document with Ceiling details to this folder. https://drive.google.com/drive/folders/1V7Y1r61s0aewc_apqbUpidFv54ClhyrK

Question 10

Posted: 4/20/2020

Question: Is a Performance & Payment bond requirement for this RFP?

Response: No

Question 11

Posted: 4/20/2020

Question: Will this site require the awarded bidder to provide a Georgia LVT Permit from the Local AHJ?

Response: I don't see anything in the RFP requiring it but anyone in GA engaging in low voltage cabling installation is required by state law to have a licensed person on staff to at least oversee the projects.

Question 12

Posted: 4/20/2020

Question: Questions Concerning - Section 6.0 Product / Service Requirements – 6.3.2 – Lockdown / Panic Buttons a. Can you please provide us with the (Quantity) & (Exact locations) of 6.3.2A – Lockdown / Panic Buttons Emergency Pull Station –SDC-492? b. Can you please provide us with the (Quantity) & (Exact location) of 6.3.2B – STI-13240CB Blue Pull Station Cover w/o horn? c. Can you please provide us with the (Quantity) & (Exact location) of 6.3.2C – FM-998 Door Holders w/ Magnets?

Response: Please review the image in the folder in 6.1.8. I have updated the image with one that include the MDF, IDF, Pull stations. You should be able to determine QTY based on that document.

Question 13

Posted: 4/20/2020

Question: ii. Expectations / Operation of all locations listed in Green (Aiphone) 1. Can you please provide us with the Aiphone exact Part #’s for the following (Aiphone Door Stations, Aiphone Master Station & Aiphone power supplies)? 2. Can you also please provide us with the Quantity of Aiphone intercoms/master stations/power supplies & the exact locations of these for this project? a. Aiphone Door Stations & (Quantity) & (Exact location) b. Aiphone Master Station & (Quantity) & (Exact location) c. Aiphone Power supply (Quantity) & (Exact location) d. Can you please provide exact Aiphone intercom counts?

Response: AiPhone is not part of this RFP

Question 14

Posted: 4/20/2020

Question: iii. Expectations / Operation of all locations listed in Blue (Lock Down & Card Reader) 1. Can you please provide the operation of how the double door will work on this lockdown? a. (Do you want a Door Contact on both Doors?) 2. Can you please list the operation function of the Single doors for this lockdown? 3. Can you please list exact counts for the lock downs on this project? b. Can you please provide us with customer expectations on where the S2 head end equipment & Power Supplies will be placed / installed (MDF/IDF’s) to accommodate all doors listed for this project? We will need to know this to be able to come up with the cabling footages.

Response: S2 controller and power supplies must be located in the MDF unless OEM cable distance specification are exceeded. If your proposal exceeds your proposed cable limits please propose an alternate location in the nearest IDF.

Question 15

Posted: 4/22/2020

Question: 1. Do we need to cover electric strikes in the proposal or will the door hardware contractor be providing them? 2. Just to confirm no Aiphone will be included in these quotes as it was apart of a RFP previously posted?

Response: The strikes will be provided by the door hardware contractor. Correct the AIPhone was in another Bid.

Question 16

Posted: 4/22/2020

Question: Does WCSD require per this RFP the awarded bidder as part of their Scope to handle creating & adding the entire database cardholder entry & assigning all of the required schedules into the new S2 Access Control software? If the answer is yes how many cardholders & how many different schedules will the awarded bidder be required to add to the new S2 database?

Response: We have a server that maintains all badges and allocations. You will be responsible for adding all door access locations to the new system and modifying anything needed to make them functional. WCS technology dept will assist where needed.

Posted: 4/20/2020

Question: Can this work be done over the summer while students are out of school?

Response: This is a new building. No students present.

Posted: 4/20/2020

Question: Training- What is required for this project? How many attendees and hours?

Response: There should only need to be training if you are offering something other than S2 and AiPhone. If you propose a different system, then you specify what training you would offer.

Posted: 4/20/2020

Question: Is WCSD providing the Aiphone Programming?

Response: No, we will assist with IP, VLan and network information needed to configure and setup the system, but you will need to provide the install.

Posted: 4/20/2020

Question: Is WCSD providing the S2 Programming?

Response: No, we will assist with IP, VLan and network information needed to configure and setup the system, but you will need to provide the install.

Posted: 4/20/2020

Question: Is there an existing Access control system at this site? If yes is demo required and please provide exactly what devices would need to demo.

Response: This is a new building

Posted: 4/20/2020

Question: Is this project New Construction or an existing site?

Response: New Construction

Posted: 4/20/2020

Question: Does your existing main S2 controller have any spare capacity in it? If so how many spare licenses are there? Do we need to provide any S2 licensing for this project? If so how many licenses?

Response: No existing system

Posted: 4/20/2020

Question: Is there any conduit work that will be required for this installation? If so can you please elaborate on exact locations and approximate footages? a. Can you please provide us the estimated number of Wall Penetrations/Fire wall penetrations that would be needed for this project? b. Will there be any MDF / IDF Wall Penetrations or sleeves needed for this project? c. Will be there by any Conduit at Door locations needed for this project? If yes how many doors would require it & would this need to be provided by us or others?

Response: All penetrations are covered under Electrical Contractor.

Posted: 4/20/2020

Question: Will the site require a lift? If so can you please provide us with the type of lift (Size) that would work? Or if it is easier can you please provide us with the ceiling heights of areas that will require a lift?

Response: Assume you will need a lift in your quote. If if your responsibility to determine what lift is needed. We will add a drawing with MDF/IDF marked as well as a document with Ceiling details to this folder. https://drive.google.com/drive/folders/1V7Y1r61s0aewc_apqbUpidFv54ClhyrK

Posted: 4/20/2020

Question: Is a Performance & Payment bond requirement for this RFP?

Response: No

Posted: 4/20/2020

Question: Will this site require the awarded bidder to provide a Georgia LVT Permit from the Local AHJ?

Response: I don't see anything in the RFP requiring it but anyone in GA engaging in low voltage cabling installation is required by state law to have a licensed person on staff to at least oversee the projects.

Posted: 4/20/2020

Question: Questions Concerning - Section 6.0 Product / Service Requirements – 6.3.2 – Lockdown / Panic Buttons a. Can you please provide us with the (Quantity) & (Exact locations) of 6.3.2A – Lockdown / Panic Buttons Emergency Pull Station –SDC-492? b. Can you please provide us with the (Quantity) & (Exact location) of 6.3.2B – STI-13240CB Blue Pull Station Cover w/o horn? c. Can you please provide us with the (Quantity) & (Exact location) of 6.3.2C – FM-998 Door Holders w/ Magnets?

Response: Please review the image in the folder in 6.1.8. I have updated the image with one that include the MDF, IDF, Pull stations. You should be able to determine QTY based on that document.

Posted: 4/20/2020

Question: ii. Expectations / Operation of all locations listed in Green (Aiphone) 1. Can you please provide us with the Aiphone exact Part #’s for the following (Aiphone Door Stations, Aiphone Master Station & Aiphone power supplies)? 2. Can you also please provide us with the Quantity of Aiphone intercoms/master stations/power supplies & the exact locations of these for this project? a. Aiphone Door Stations & (Quantity) & (Exact location) b. Aiphone Master Station & (Quantity) & (Exact location) c. Aiphone Power supply (Quantity) & (Exact location) d. Can you please provide exact Aiphone intercom counts?

Response: AiPhone is not part of this RFP

Posted: 4/20/2020

Question: iii. Expectations / Operation of all locations listed in Blue (Lock Down & Card Reader) 1. Can you please provide the operation of how the double door will work on this lockdown? a. (Do you want a Door Contact on both Doors?) 2. Can you please list the operation function of the Single doors for this lockdown? 3. Can you please list exact counts for the lock downs on this project? b. Can you please provide us with customer expectations on where the S2 head end equipment & Power Supplies will be placed / installed (MDF/IDF’s) to accommodate all doors listed for this project? We will need to know this to be able to come up with the cabling footages.

Response: S2 controller and power supplies must be located in the MDF unless OEM cable distance specification are exceeded. If your proposal exceeds your proposed cable limits please propose an alternate location in the nearest IDF.

Posted: 4/22/2020

Question: 1. Do we need to cover electric strikes in the proposal or will the door hardware contractor be providing them? 2. Just to confirm no Aiphone will be included in these quotes as it was apart of a RFP previously posted?

Response: The strikes will be provided by the door hardware contractor. Correct the AIPhone was in another Bid.

Posted: 4/22/2020

Question: Does WCSD require per this RFP the awarded bidder as part of their Scope to handle creating & adding the entire database cardholder entry & assigning all of the required schedules into the new S2 Access Control software? If the answer is yes how many cardholders & how many different schedules will the awarded bidder be required to add to the new S2 database?

Response: We have a server that maintains all badges and allocations. You will be responsible for adding all door access locations to the new system and modifying anything needed to make them functional. WCS technology dept will assist where needed.