Description: This quote request is for the demolish and removal of the Old Visitor Information Center located at 735 Via De Luna Drive on Pensacola Beach. This quote needs to include the asbestos survey, demolition of the building, removal of all demo debris and any applicable permits. Contractor needs to be aware that any demo performed must be removed from the island the same day. No stockpiles will be allowed overnight. The County will need this work performed during October 2018.
Products:
- Demolition Services
Addition 1
Name: Award Information
Posted: 10/3/2018
Question 1
Posted: 9/17/2018
Question: How do the bids need to be submitted?
Response: The bids are uploaded through the vender registry link that was provided.
Question 2
Posted: 9/14/2018
Question: Is there going to be a walk-through? Is any asbestos going to be removed through another bid or a change order? Any bid bonding required?
Response: Under $25,000 does not require a bond. As part of the quote, the contractor must perform an asbestos survey. If mitigation is required a separate quote will be obtained.
Question 3
Posted: 9/14/2018
Question: Does any concrete outside of the building foot print need to be removed? Does fill need to be brought in and sodded/seeded? Construction fence required around the work zone?
Response: No concrete outside of the building needs to be removed at the time of demo. No fill is required however the area will need to be graded flat and clean of debris. Construction fence during demo is recommended,
Addition 1
Name: Award Information
Posted: 10/3/2018
Posted: 9/17/2018
Question: How do the bids need to be submitted?
Response: The bids are uploaded through the vender registry link that was provided.
Posted: 9/14/2018
Question: Is there going to be a walk-through? Is any asbestos going to be removed through another bid or a change order? Any bid bonding required?
Response: Under $25,000 does not require a bond. As part of the quote, the contractor must perform an asbestos survey. If mitigation is required a separate quote will be obtained.
Posted: 9/14/2018
Question: Does any concrete outside of the building foot print need to be removed? Does fill need to be brought in and sodded/seeded? Construction fence required around the work zone?
Response: No concrete outside of the building needs to be removed at the time of demo. No fill is required however the area will need to be graded flat and clean of debris. Construction fence during demo is recommended,